Additional Harbor Access on the May 3 City Council Agenda

The Punta Gorda City Council has made this announcement today in their weekly “City Highlights from April 7, 2017”: “And mark your calendars for the May 3 Council meeting, at 9:00 a.m. for an update on the “Alternate Harbor Access”...

Update on “Alligator Creek Access”

2016 End of Year Progress Report The following is an update summary of the “Additional Harbor Access” (aka Bird Cut), the project now managed by the City of Punta Gorda. This information was submitted by Hans Wilson, P.A. to Boaters Alliance and approved...

Sept. 15th, 2016: Additional Harbor Access Update

Thank you Gary Disher, from the PG City Works Dept., for updating the PGBA about the status of the Additional Harbor Access at the general membership meeting Sept. 15th. Accordingly, it was noted that Hans Wilson of Hans Wilson & Associates has submitted the...

Additional Harbor Access Update

July 29th City Manager’s Report had the following update to activities for the Additional Harbor Access (Alligator Creek Access): “PGI Additional Access to Charlotte Harbor: Field work was completed and channel design has been finalized. City staff and the...

Additional Harbor Access: 3-4 years?

A note from the Alligator Creek Access Committee, ad hoc committee under Punta Gorda Boaters Alliance May 17, 2016: You may have heard recently that the Punta Gorda City Council is telling the local real estate agents that possible construction of the Bird Cut East...

Additional Harbor Access discussed at the City Council Meeting

Synopsis from the May 4th, 2016 Wednesday City Council meeting, per the Additional Harbor Access: “…Approved an agreement with a legal firm to work with City staff for the establishment of an assessment program/methodology for the Additional Harbor Access...